Introduction

A museum needs a reusable label holder for 100 display days. Compare a sealed product with a version that can be repaired, then build a realistic project plan. You will use fictional impact values to make a conditional recommendation and use task dependencies to decide when a design review can happen.


Compare products that deliver the same service

First define what the product must do. The service for this study is one stable, readable label position for 100 display days in the same indoor setting. Comparing the environmental impacts of one sealed holder with one serviceable holder can mislead if they need different replacements to deliver that service. Compare the actual number of units and inserts required over the same period.

A life-cycle assessment asks about impacts across a defined system. Decide what enters the calculation, then gather data for raw materials, manufacture, transport, use and the end of the product’s use. The simplified classroom model includes replacement inserts in the use and service stage. A real study may examine several environmental indicators and document wider effects and assumptions. Here the numerical example tracks greenhouse gas emissions in kilograms of carbon dioxide equivalent, written kg CO₂e.

Video route. Pick one life-cycle stage shown in the explanation and decide what evidence the museum would need for it. Written route. For transport, estimate journeys and distances using the same service target. For service, count how many inserts or complete units must be supplied. Keep the treatment of both options consistent.


Plan for repair, reuse and material recovery

A sealed assembly may be quick to make and easy to handle. If a small part fails and cannot be replaced, the whole assembly may need to be substituted. Designing a replaceable insert can extend useful life. It may require a thicker enclosure, stock of inserts or additional fasteners. Consider whether the insert is actually accessible, whether appropriate parts will be available and who can carry out the repair.

Several rectangular bales of compressed aluminium cans are stacked ready for recycling
Collection and compression are steps on a possible material-recovery route.

The photo shows collected material before further processing. Recycling requires that a suitable collection and processing route exists. A claim about recoverability needs evidence of the material, the route and the actual conditions. Reuse keeps an item in service. Repair restores function. Recycling processes materials so they can be used again. All can involve transport and work.

Write one testable design question. For example, can the label insert be removed and installed again without damage, and does the assembled product still meet the stability requirement? Plan to record any damaged fasteners, time needed and whether the parts can be separated by material at the end of use.


Calculate and challenge a life-cycle comparison

The team’s synthetic inventory assumes two sealed holders or one serviceable holder plus one planned insert to provide the same 100 display days. All entries are totals for that service. In this model the final row counts end-of-life handling impacts. It assigns no speculative avoided-impact credit from recycling.

Stage Sealed option in kg CO₂e Serviceable option in kg CO₂e
Materials 2.8 2.2
Manufacture 1.8 1.5
Transport 0.6 0.5
Use and service 0.2 0.7
End-of-life handling 0.4 0.2

The stage totals are 5.8 kg CO₂e for the sealed option and 5.1 kg CO₂e for the serviceable option. The latter is 0.7 kg CO₂e lower in this model. If an unexpected repair requires one extra insert with an additional net 0.9 kg CO₂e within the same boundary, the serviceable total rises to 6.0 and the ranking reverses. That sensitivity tells you which assumption to investigate before the team commits.

This inventory describes a carbon indicator under synthetic assumptions. It does not rank water use, waste, cost, worker conditions or durability by itself. Add those dimensions explicitly if they affect the decision. Record which data are estimated and what might change the comparison.


Read dependencies and time the project

A production plan gives each task an owner, a start, a duration, the resources it needs and the evidence that it is finished. A dependency means that a task needs some earlier task or output first. A milestone marks a point such as approval of the brief. On a Gantt chart, horizontal bars show the scheduled task intervals. On a chart with dependency arrows you can also see which finishes make subsequent starts possible.

Seven task rows have horizontal bars and arrows connecting example start and finish dates
Find two tasks that overlap and one arrow connecting a predecessor to a later task.

The displayed schedule is an independent example. For the classroom plan below, assume the supplier comparison and the design sketches can use different people at the same time. The units are session durations. The first task starts at time zero.

Task Work Duration Prerequisites
A Agree the brief 2 None
B Compare material suppliers 3 A
C Sketch design alternatives 2 A
D Develop the virtual prototype 3 B and C
E Simulate and evaluate 2 D
F Final review 1 E

B and C can start at time 2. B finishes at 5 and C finishes at 4, so D starts at 5. The earliest finish is time 11. The duration-driving sequence is A, B, D, E, F. If C is delayed by one session and everything else stays the same, D can still start at 5. If B is delayed by one, D moves to 6 and the earliest finish to 12.

Video route. Find how a start and duration are shown on a Gantt chart. Then compare that layout with your own plan. Written route. Draw the six task names down the page and time from 0 to 11 across it. Draw B from 2 to 5 and C from 2 to 4. Add an arrow from both finishes to the start of D.


Make a bounded recommendation and plan a review

Give the museum a conditional decision. The serviceable holder is the lower-carbon option in the baseline table. Check first whether its expected insert life is realistic. Test the virtual assembly to see whether it remains stable after a simulated repair. Keep the sealed design as a comparison if actual repair assumptions change.

A resource plan also needs a budget. A fictional class allocation allows £50. Materials cost £35, consumables or fixture use cost £8 and contingency is £5. The planned total is £48, leaving £2. Recheck the total if the comparison adds a cost or a new task. A proposed change needs an owner, a finish date and an acceptance check.

Include a review gate after E. Review the stability evidence, the maintenance assumption and any cost or schedule change. The final review records what passed, what is still uncertain and which product and process changes the next version should test. This lesson produces a simulation and planning record for a classroom brief.


Interactive Tasks


Quiz: Test Your Knowledge

What must be held equivalent when comparing the two holders? (The service of one stable label for 100 display days) (!The number of products regardless of their lifetime) (!The price of every fastener) (!The shape of the recycling bale)



What is the total for the sealed baseline option? (5.8 kg CO₂e) (!5.1 kg CO₂e) (!5.0 kg CO₂e) (!6.7 kg CO₂e)



What is the baseline advantage of the serviceable option for the carbon indicator? (0.7 kg CO₂e lower) (!0.7 kg CO₂e higher) (!0.9 kg CO₂e lower) (!The totals are equal)



What happens after including an extra 0.9 kg CO₂e insert for the serviceable option? (Its 6.0 total exceeds the sealed option’s 5.8) (!Its 4.2 total is below the sealed option’s 5.8) (!Both options increase to 6.0) (!The serviceable option stays at 5.1)



What does the recycling photograph by itself confirm? (The shown cans were collected and compressed) (!Every possible waste stream will recycle the museum holder) (!There are no emissions from reprocessing the metal) (!A specific climate saving for both designs)



Which tasks must finish before D can begin? (B and C) (!A and F) (!Only E) (!D and E)



When is the earliest start for task D in the original plan? (Time 5) (!Time 4) (!Time 3) (!Time 6)



What happens if task C alone takes one more session? (The earliest overall finish stays at time 11) (!The plan finishes one session earlier) (!The overall finish moves to time 13) (!Task D must start one session before C ends)



How much of the £50 allocation remains after all planned amounts including contingency? (£2) (!£5) (!£7) (!£12)



Which check most directly helps test the carbon result’s main uncertainty? (Verify whether another replacement insert is likely) (!Remove the lower result from the calculation table) (!Compare the projects only by their review dates) (!Increase the project budget without checking resource use)





Memory Game

Baseline sealed option 5.8 kg CO₂e for the defined service
Baseline serviceable option 5.1 kg CO₂e for the defined service
Serviceable option with the additional insert 6.0 kg CO₂e in the sensitivity case
Earliest completion of task B Time 5
Earliest end of the original plan Time 11





Drag and Drop

Hold output constant between alternatives Same 100 display days
Find important assumptions that change a conclusion Sensitivity comparison
Return a damaged product to useful service Repair
Show task durations on a timeline Gantt chart
Record whether agreed criteria have been met Project review





Crossword Puzzle

REPAIR Restore function to an item with a damaged part
REUSE Use an existing item again
RECOVERY Obtaining useful material from a product after use
BOUNDARY Limit of what a life-cycle comparison includes
MILESTONE Named point that marks progress at a planned time
BUDGET Planned financial allocation for a project





LearningApps

Optional extra practice. Choose an appropriate activity with your teacher. If the external collection is unavailable, use the native activities and independent tasks in this course.


Cloze Text

Complete the explanation.
A comparison needs the same

from both options. An impact count across defined stages is a

. Restoring function by replacing a damaged insert is

. A task that requires earlier work has a

. A Gantt chart uses horizontal

to show timing. Money set aside for possible unexpected cost is

.



Open Tasks


Easy

  1. State the service: Write one sentence describing the service both holders must provide in the comparison.
  2. Name an included stage: Choose a stage of production or use and name one input to measure.
  3. Find a predecessor: Read the plan and name the task that must finish before the sketches start.
  4. Mark a milestone: Add the point at which the class agrees the brief to a simple timeline.


Standard

  1. Calculate both totals: Sum the impact columns and write which values are assumptions in the classroom example.
  2. Compare repair and reuse: Write one way a replaceable insert can extend useful life and one condition that needs to hold.
  3. Draw a baseline schedule: Plot the six tasks on a Gantt chart from time 0 and show both prerequisites for developing the prototype.
  4. Show a simple budget: Calculate what happens to the funds remaining if the fixture cost increases by £2.


Advanced

  1. Find the reversal point: Find the upper value an additional repair can add before the serviceable option loses its baseline lower-carbon position.
  2. Remove a resource assumption: Suppose the same person must complete B and C in sequence. Work out the earliest project finish and explain the change.
  3. Improve the inventory: Select two estimates to replace with evidence. Specify how to collect each value under the same service definition.
  4. Present a project review: Write a concise review with one conditional decision, one impact comparison, the next investigation and an owner and deadline.



Learning Check

  1. Make a fair comparison: A supplier compares one 50-day holder with one 100-day holder. Explain a better comparison for the museum.
  2. Recalculate a sensitivity case: An additional inspection adds 0.4 kg CO₂e only to the serviceable option. How does it compare with the sealed baseline?
  3. Check a delayed dependency: Task B takes four sessions instead of three. When can D start and when can the project finish?
  4. Evaluate a budget change: A £3 charge appears before the review. With the planned contingency still ring-fenced, compare the total with the original budget.
  5. Explain impact scope: Why can the lower carbon total fail to settle the design decision?
  6. Plan a milestone check: What record should be available at the milestone after task E?


Worked checks and assessment guidance

  1. Estimate how many holders and inserts are needed to provide the same 100 days, then compare the two total inventories within the same boundary.
  2. The total is 5.5 kg CO₂e. It is 0.3 kg CO₂e below the sealed case at 5.8 under these assumptions.
  3. B finishes at 6 while C finishes at 4. D starts at 6. The durations of D, E and F add six sessions, so the earliest finish is 12.
  4. The planned total becomes £51, which is £1 above the £50 budget. Review the cost or amend the allocation with approval before claiming the project is within budget.
  5. The indicator does not quantify every relevant outcome. The choice also depends on evidence such as stability, repair feasibility, water use, cost or material recovery.
  6. Keep the simulation results, their pass criteria and the uncertainties about maintenance, costs and schedule. The review can then decide whether changes are needed before closing the project.


Learning evidence

Submit a service-based comparison, a stage table, a sensitivity calculation and a Gantt chart with both dependencies recorded for the prototype. Justify a conditional choice and explain one measurement that would improve it.


OER and Wikipedia

Department for Education, GCSE engineering subject content. AQA, Impact of modern technologies. AQA, Production planning. The impact inventory, costs and task durations are synthetic.

Compressed aluminium cans, Tycho, CC0 1.0. Gantt chart example, Vheilman, CC BY-SA 3.0. Wikimedia Commons.

GCSE Chemistry – Life Cycle Assessments, Cognito. GCSE D&T NEA walkthrough development Gantt Chart, MR Ridley Design & Technology. Both have written alternatives.

iFrame blockiert

Diese externe Quelle ist für aiMOOC-iFrames nicht freigegeben.


Linked learning areas


aiMOOC Projects



Schulfach+




aiMOOCs



aiMOOC Projekte